AS/NZS 5131 CC2 Quality Process for Structural Steel.

Six fabrication stages, five hold points, one Manufacturer's Data Report. Every structural steel package leaving 8 Star is built to AS/NZS 5131 Construction Category 2 — with the records that prove it bundled into an MDR for your engineer and certifier.

Standard

AS/NZS 5131

Category

CC2 Default

Stages

06

Hold Points

05

Deliverable

MDR

NDT

3rd-Party

AS/NZS 5131 Fabrication Categories

Three construction categories define quality and inspection rigour. We default to CC2 for structural steel work.

CC1

Non-Structural

Light, non-load-bearing fabrications and architectural trim

CC2

Standard Structural

Commercial, industrial and architectural structural steel — our default

8 Star Default

CC3

Critical Structural

Crane-loaded portals, fatigue-loaded or high-consequence structures — available where engineer-specified

AS/NZS 5131 CC2 Quality Process — Stage by Stage

Six stages between raw steel arriving at the workshop and steelwork signed off at dispatch. Five hold points sit between them. A hold point means the steel doesn't progress to the next stage until the previous one is inspected and recorded.

01 MATERIAL RAW IN Mill certs received HP-1 02 CUT/PREP CUT & DRILL To engineer's drawings HP-2 03 WELD WELD AS/NZS 1554.1 HP-3 04 INSPECT INSPECT Visual + 3rd-party NDT HP-4 05 FINISH GALV/PAINT AS/NZS 4680 HP-5 06 DISPATCH SIGN-OFF MDR handover
Process Stage Hold Point — inspection & record before progressing Final Sign-off & Documentation Handover

Quality Hold Points and Inspection Checks

Five hold points between the six fabrication stages. Each is a place where the steel doesn't move forward until the previous step is checked and the check is recorded against the job.

HP
Stage Transition
What We Check
What We Record

HP-1

Material In → Cut & Prep

Before any cutting happens

  • Mill cert matches order spec
  • Batch / heat number recorded
  • Grade and length verified
  • Mill cert filed with job
  • Material received note

HP-2

Cut & Prep → Weld

Before welding starts

  • Members cut to drawing dimensions
  • Hole positions verified
  • Edge prep ready for weld procedure
  • Dimensional check sheet
  • Drawing revision number on file

HP-3

Weld → Inspect

After all welds laid down

  • Welder self-check completed
  • Job ready for QA visual
  • Third-party NDT request issued if engineer-specified
  • Welder details against the job
  • Third-party NDT request reference

HP-4

Inspect → Finish

Before paint or galvanising

  • Visual inspection passed
  • Third-party NDT result reviewed (where specified)
  • No re-work outstanding
  • Visual inspection notes
  • Third-party NDT report attached to job

HP-5

Finish → Dispatch

Before steel leaves the workshop

  • Galv coating thickness checked
  • Paint dry-film thickness recorded
  • Final piece count against schedule
  • Galvanising certificate
  • Dispatch sign-off sheet

Documentation We Build Through Fabrication

Each hold point adds a record to the job file. By the time steel ships from the workshop, the handover pack is built — engineer and certifier receive it bundled at dispatch.

Documents Built Into the MDR

  1. Mill Certificates

    Added at HP-1 (Material In)

  2. Dimensional Check Sheet

    Added at HP-2 (After Cut & Prep)

  3. Welder & Weld Reference

    Added at HP-3 (After Weld)

  4. Inspection Notes + NDT Report

    Added at HP-4 (After Inspection)

  5. Coating & Galvanising Records

    Added at HP-5 (After Finish)

  6. Dispatch Sign-off & Bundle

    Final at Stage 06 (Dispatch)

One MDR. One hand-over. No follow-up requests.

Bundled into a Manufacturer's Data Report (MDR) — the industry-standard format your engineer and building certifier already know how to review. The pack isn't built at the end — it's built up during the job, every record filed as it's produced, against the job number and drawing revision.

By the time the truck leaves the workshop, the MDR is ready. We hand it over in one go — your engineer and certifier don't need to chase us for mill certs three weeks later, or ask "did you NDT that bolt group" six months after install.

If you need a sample MDR to review before engaging us, request one with your tender drawings — we'll redact client details and send a previous job's documentation set.

Audit-Ready Records Your Engineer Can Request

Five questions engineers and building certifiers ask most often when auditing a structural steel package. Our answer to each is the same — yes, here it is.

Q1Can you show me the mill cert for the parent steel on this beam?

Yes — mill certificate filed against the job at HP-1, batch number traceable to the original supplier. Heat number is on the cert and on the piece itself.

Q2Who welded this connection, and to what standard?

Welder details are recorded against the project at HP-3. All welds laid to AS/NZS 1554.1 by Australian-trade-qualified welders (MEM30305 or equivalent).

Q3Has this weld been visually inspected? Where's the record?

Visual inspection notes filed at HP-4, against AS/NZS 1554.1 acceptance criteria. Done before paint or galvanising goes on, so the weld surface was visible.

Q4If you NDT-tested this butt weld, who did it and what's the report?

NDT is performed by a third-party NDT operator where the engineer nominates it. The original NDT report sits in the MDR — operator, date, method (UT or MT), result. The third-party arrangement means the inspection isn't done by the same shop that did the welding.

Q5Was this drawing revision the one fabricated to?

Yes — drawing revision number is recorded at HP-2 against the dimensional check sheet, and again on the dispatch sign-off. If the engineer issued a revised drawing mid-job, the change is logged.

Quote with AS/NZS 5131 MDR Included by Default

Send your structural drawings — we'll respond with a quote that includes the AS/NZS 5131 CC2 Manufacturer's Data Report handed over at dispatch. Sample MDRs from previous jobs available on request.